Fakta om udbudet
Bestilling af materiale
http://eu.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=371961&B=KEFM
Udbyder
Energistyrelsen
3 GW Energy Island Bornholm - Denmark - Market Dialogue
Energistyrelsen
Prior information notice
This notice is for prior information only
Works
Section I: Contracting authority
National registration number: 59778714
Postal address: Carsten Niebuhrs Gade 43
Town: København V
NUTS code: DK Danmark
Postal code: 1577
Country: Denmark
Contact person: Michal Andrzej Orcelek
E-mail: mcck@ens.dk
Internet address(es):
Main address: www.ens.dk
Address of the buyer profile: https://eu.eu-supply.com/ctm/Company/CompanyInformation/Index/414838
Section II: Object
3 GW Energy Island Bornholm - Denmark - Market Dialogue
The Danish Energy Agency invites potential tenderers and relevant economic operators to participate in the market dialogue regarding the upcoming procurement of Energy Island Bornholm, which will serve as a hub to collect and distribute green power from offshore wind turbines. On the island of Bornholm, the current is transformed and then transported initially to Zealand and Germany. The upcoming procurement, which this market dialogue concerns, covers the establishment of two (2) new large-scale offshore wind farms in connection with the Energy Island Bornholm, named Energy Island Bornholm I and II.
For further information regarding the upcoming procurement, reference is made to section II.2.4) below and the procurement material. See also section VI.3) below for more information regarding the procedure for the market dialogue.
Energy Island Bornholm I
The upcoming procurements concern two (2) offshore wind farms. Energy Island Bornholm I and II are located as illustrated in the procurement material, Appendix 3 to Annex F Draft of the Concession Agreement.
The minimum capacity of Energy Island Bornholm I and II are 1GW and 2 GW, respectively, and shall be constructed before 31.12.2030.
The minimum capacity of the offshore wind farms is required to be connected to the public electricity grid, and it will be possible to install overplanting capacity limited 200 MW for Energy Island Bornholm I and 600 MW for Energy Island Bornholm II.
Further reference is made to the procurement material regarding the requirements to the offshore wind farms.
The upcoming procurement will be carried out as an open procedure, pursuant to the Danish Public Procurement Act, Act no. 10 of 6 January 2023 with subsequent amendments. The details regarding the procurement procedure are stated in the Procurement Specifications.
Energy Island Bornholm II
The upcoming procurements concern two (2) offshore wind farms. Energy Island Bornholm I and II are located as illustrated in the procurement material, Appendix 3 to Annex F Draft of the Concession Agreement.
The minimum capacity of Energy Island Bornholm I and II are 1GW and 2 GW, respectively, and shall be constructed before 31.12.2030.
The minimum capacity of the offshore wind farms is required to be connected to the public electricity grid, and it will be possible to install overplanting capacity limited 200 MW for Energy Island Bornholm I and 600 MW for Energy Island Bornholm II.
Further reference is made to the procurement material regarding the requirements to the offshore wind farms.
The upcoming procurement will be carried out as an open procedure, pursuant to the Danish Public Procurement Act, Act no. 10 of 6 January 2023 with subsequent amendments. The details regarding the procurement procedure are stated in the Procurement Specifications.
Section IV: Procedure
Section VI: Complementary information
The market dialogue is initiated in coorperation with Energinet and will be carried out in writing, with the scope of collecting input to the draft of the procurement material from the market. The draft of the procurement material is published by the Danish Energy Agency via EU-Supply, cf. section 1.3) above.
All communication during the market dialogue will take place via EU-Supply. The information uploaded to EU-Supply will be updated during the market dialogue.
The Danish Energy Agency and Energinet has formulated a list of questions to the participants in the market dialogue, which can be found in the excel-file, "Input to market dialogue - 3 GW Energy island Bornholm", under the sheet “Questions to market”, uploaded with the procurement material on EU-Supply. Furthermore, the participants can submit questions and comment on the draft of the procurement material as a whole.
It should be noted that the procurement material in its entirety is in a draft, but that elements of the procurement material has been marked with sharp brackets and in gray, which indicate elements that are still under consideration. Input to these elements are in particular welcomed.
The participants must use the excel-file, "Input to market dialogue - 3 GW Energy island Bornholm", under the sheet “Comments from market”, uploaded with the procurement material on EU-Supply in order to submit questions and comments to the procurement material. The module, “Messages”, in EU-Supply, may be used to attach and submit the completed excel-file.
The Danish Energy Agency welcomes the feedback from the participants before the end of August 2023
After the completion of the written market dialogue the Danish Energy Agency and Energinet will host technical meetings with the scope of having a dialogue regarding the requirements stated in the procurement material, hereunder grid connection and overplanting. Further information regarding the specific themes and circumstances of the technical meetings will be published later via EU-Supply.
Regarding section II.1.5): The Estimated total value stated in section II.1.5) above, covers the total estimated value of the two (2) offshore wind farms. It is accentuated that it is only a preliminary estimate.
Regarding section II.1.6): It is accentuated, that the procurement will be divided into lots, as stated in section II.1.6) above, with the scope of entering into agreement regarding two (2) separate contracts. Further reference is made to the procurement specifications.
Regarding section II.3): The Estimated date of publication of the concession notice stated in section II.3) is only preliminary and may be changed for the upcoming procurement procedures. The attention of the participants to the market dialogue is also drawn to the questions regarding the time schedule of the upcoming procurement procedure in the excel-file, "Input to market dialogue - 3 GW Energy island Bornholm", under the sheet “Questions to market”, uploaded with the procurement material on EU-Supply.