Fakta om udbudet

EU-nr
2022/S 032-083163
Offentliggjort
15.02.2022
Udbudstype
Udbud med forhandling uden forudgående offentliggørelse

Udbyder

Energinet Eltransmission

Vindere

(15.02.2022)
GE Grid Solutions
Jupitervej 6
6000 Kolding

Cable bay for extension of current GE Grid Solutions GIS-unit


Energinet Eltransmission

Voluntary ex ante transparency notice

Supplies

Legal Basis:
Directive 2014/25/EU

Section I: Contracting authority/entity

I.1) Name and addresses
Official name: Energinet Eltransmission
National registration number: 39314878
Postal address: Tonne Kjærs Vej 65
Town: Fredericia
NUTS code: DK Danmark
Postal code: 7000
Country: Denmark
Contact person: Procurement - R
E-mail: indkob@energinet.dk
Telephone: +45 70102244
Internet address(es):
Main address: https://eu.eu-supply.com/ctm/supplier/publictenders?B=ENERGINET
I.6) Main activity
Electricity

Section II: Object

II.1) Scope of the procurement
II.1.1) Title:

Cable bay for extension of current GE Grid Solutions GIS-unit

Reference number: 21/06723
II.1.2) Main CPV code
31170000 Transformers
II.1.3) Type of contract
Supplies
II.1.4) Short description:

Cable bay for extension of current GE Grid Solutions GIS-unit and two voltage transformers including installation and gas.

II.1.6) Information about lots
This contract is divided into lots: no
II.1.7) Total value of the procurement (excluding VAT) (Agree to publish? yes)
Value excluding VAT: 4 000 000.00 DKK
II.2) Description
II.2.3) Place of performance
NUTS code: DK Danmark
Main site or place of performance:

Avedøreværket, Hammerholmen 50, 2650 Hvidovre

II.2.4) Description of the procurement:

Procurement of 132kV GIS plant og two PQ-compatible GIS voltage transformers with RCD including installation and commissioning to an existing plant on 132kV substation Avedøreværket, as well as filling of gas.

II.2.5) Award criteria
II.2.11) Information about options
Options: no
II.2.13) Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: no
II.2.14) Additional information

Section IV: Procedure

IV.1) Description
IV.1.1) Type of procedure
Negotiated procedure without prior call for competition
  • Additional deliveries by the original supplier ordered under the strict conditions stated in the directive
Explanation:

GE delivered the existing installation at the 132 kV substation Avedøreværket in 2019.

The technical drawings of the substation are the property of GE and can therefore not be handed over to another supplier. Consequently, supplies originating from other sup-pliers are assessed to result in incompatibility or disproportionate technical difficulties in operation and maintenance as another supplier would have to completely disconnect the system to make the necessary technical examinations and adjustments (if at all pos-sible). Further, when the substation was installed by GE, an extension, corresponding to the one now needed from GE, was included in the design. The technical environment constituting the 132 kV substation Avedøreværket has been constructed in correspondence with said design and any changes thereto would therefore compromise the re-quired clearance distance to other, already installed, critical equipment on the station.

As the substation Avedøreværket is critical for security of supply in Copenhagen, and as a consequence of the reasons stated above, the Contracting Authority has assessed that a legal basis for the award can be found in article 50 (e) of the directive 2014/25/EU.

IV.1.3) Information about framework agreement
IV.1.8) Information about the Government Procurement Agreement (GPA)
The procurement is covered by the Government Procurement Agreement: yes
IV.2) Administrative information

Section V: Award of contract/concession

V.2) Award of contract/concession
V.2.1) Date of contract award decision:
10/02/2022
V.2.2) Information about tenders
The contract has been awarded to a group of economic operators: no
V.2.3) Name and address of the contractor/concessionaire
Official name: GE Grid Solutions
National registration number: 27550835
Postal address: Jupitervej 6
Town: Kolding
NUTS code: DK Danmark
Postal code: 6000
Country: Denmark
The contractor/concessionaire will be an SME: no
V.2.4) Information on value of the contract/lot/concession (excluding VAT) (Agree to publish? yes)
Total value of the contract/lot/concession: 4 000 000.00 DKK
V.2.5) Information about subcontracting

Section VI: Complementary information

VI.3) Additional information:
VI.4) Procedures for review
VI.4.1) Review body
Official name: Klagenævnet for Udbud
Postal address: https://naevneneshus.dk/start-din-klage/klagenaevnet-for-udbud/
Town: Viborg
Postal code: 8800
Country: Denmark
Telephone: +45 72405708
VI.4.3) Review procedure
Precise information on deadline(s) for review procedures:

Complaints regarding a candidate not being pre-qualified must be filed with The Complaints Board for Public Procurement within 20 calendar days starting the day after the contracting authority has sent notification to the candidates involved, provided that the notification includes a short account of the relevant reasons for the decision.

Other complaints must be filed with The Complaints Board for Public Procurement within:

1. 45 calendar days after the contracting authority has published a contract award notice in the Official Journal of the European Union (with effect from the day following the publi-cation date);

2. 30 calendar days starting the day after the contracting authority has informed the ten-derers in question, that the contracting authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing sys-tem, provided that the notification includes a short account of the relevant reasons for the decision;

3. 6 months starting the day after the contracting authority has sent notification to the can-didates/tenderers involved that the contracting authority has entered into the framework agreement, provided that the notification included a short account of the relevant rea-sons for the decision.

4. 30 calendar days after the contracting authority has published a contract award notice in the Official Journal of the European Union which clarifies the reasons for the contract be-ing awarded without prior publication of a contract notice (when the procedure described in section 4 of the Act on the Danish Complaints Board for Public Procurement (kla-genævnsloven) has been followed).

Energinet shall follow the procedure in Section 4 of the Act on the Board of Appeal (Consolidated Act No 593 of 2.6.2016 on the Public Procurement Board of Appeal, available at: www.retsinformation.dk). Thus, the intended contract will not be concluded before the expiry of 10 calendar days with effect from the day following the date of publication of this notice, cf. Section 4 (1) (2) of the Act on the Board of Appeal.

VI.4.4) Service from which information about the review procedure may be obtained
Official name: Konkurrence- og Forbrugerstyrelsen
Postal address: Carls Jacobsens Vej 35
Town: Valby
Postal code: 2500
Country: Denmark
Telephone: +45 41715000
VI.5) Date of dispatch of this notice:
10/02/2022